| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IE-2 | DE 19 mm. DE DIAM. | M. |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBCGPD19 | TUBO CONDUIT GALV. PARED DELGADA DE 19MM | PZA | 0.350000 | $46.30 | $16.21 |
| COPLECGPD19 | COPLE CONDUIT GALV. PARED DELGADA DE 19MM | PZA | 0.333333 | $7.60 | $2.53 |
| CODOCGPD19 | CODO CONDUIT GALV. PARED DELGADA DE 19MM | PZA | 0.200000 | $11.50 | $2.30 |
| SEGUETAD/STAN | SEGUETA DIENTE STANDARD | PZA | 0.050000 | $12.30 | $0.62 |
| Suma de Material | $21.65 | ||||
| Mano de Obra | |||||
| I CUADRILLA ELECTRIC | Cuadrilla electrica (1 Of. Electricista + 1 Ayudante) | Jor. | 0.016000 | $972.72 | $15.56 |
| Suma de Mano de Obra | $15.56 | ||||
| Auxiliar | |||||
| ANDAMIO | MODULO DE ANDAMIOS HASTA 2.2 MTRS | r/d | 0.025000 | $13.28 | $0.33 |
| Suma de Auxiliar | $0.33 | ||||
| Costo Directo | $37.55 |