| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2A.2 | Plantilla,de concreto. F'c=100 Kg/cm² y de 5 cms de espesor. | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.500000 | $4.80 | $2.40 |
| CLAVO (VARIAS MED.) | CLAVO PARA MADERA VARIAS MEDIDAS | KG | 0.020000 | $17.00 | $0.34 |
| ALAMBRE REC | ALAMBRE RECOCIDO CAL. 16 | KG | 0.100000 | $15.00 | $1.50 |
| Suma de Material | $4.24 | ||||
| Mano de Obra | |||||
| CUA ALBAÑIL 2 | ( 1 ALBAÑIL + 2 PEONES ) | JOR | 0.025000 | $1,078.14 | $26.95 |
| Suma de Mano de Obra | $26.95 | ||||
| Auxiliar | |||||
| CONCRETO F-C=100 H/O | CONCRETO HECHO EN OBRA F'c = 100 KG/CM2 AGREGADO MAX. 3/4" R.N. | M3 | 0.052500 | $837.58 | $43.97 |
| Suma de Auxiliar | $43.97 | ||||
| Costo Directo | $75.17 |