| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| C7 | SUMINISTRO, FABRICACION Y MONTAJE DE POLINERIA PERFIL"CF" ACERO A441 Fy=3515 Kg/cm², INCLUYE PINTURA ANTICORROSIVA VER ESPECIFICACIÓN EN PLANO 10-08 | KG |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| IPR DIF. MEDIDAS | KG | 0.200000 | $9.90 | $1.98 | |
| VIGA HP | KG | 0.509900 | $9.90 | $5.05 | |
| PLACA 1/4"@ 1" | KG | 0.227800 | $10.64 | $2.42 | |
| CANAL ESTRUCTURAL | KG | 0.054250 | $9.00 | $0.49 | |
| ANGULO DIF. MEDIDAS | KG | 0.054250 | $9.29 | $0.50 | |
| GAS P/ CORTES | KG | 0.009000 | $5.05 | $0.05 | |
| OXIGENO | OXIGENO | M3 | 0.008500 | $70.00 | $0.60 |
| SOLDADURA E7018 | SOLDADURA E 7018 | KG | 0.007330 | $30.00 | $0.22 |
| ALAMBRE TUBULAR | KG | 0.004000 | $28.00 | $0.11 | |
| DISCO ABRASIVO | DISCO ABRASIVO | PZA | 0.002200 | $75.00 | $0.17 |
| SPOT LABORATORIO | KG | 1.000000 | $0.15 | $0.15 | |
| TORNILLERIA | TORNILLERIA | KG | 0.003600 | $60.00 | $0.22 |
| FLETES Y MANEJOS | FLETES Y MANEJOS | (%)m | 0.021350 | $0.00 | $0.00 |
| PRIMER ESTR DUCO | LT. | 0.009600 | $47.00 | $0.45 | |
| THINER | THINER | LT | 0.076190 | $12.00 | $0.91 |
| Suma de Material | $13.31 | ||||
| Mano de Obra | |||||
| CUADRILLA N° 341 | 1 of.pailero + 1 ayudante E. | JOR | 0.001333 | $722.18 | $0.96 |
| CUADRILLA N° 342 | 1 of.soldador + 1 ayudante E. | JOR | 0.001333 | $722.18 | $0.96 |
| CUADRILLA N° 346 | 1 Maniobrista + 3 Ayudantes | JOR | 0.001000 | $1,101.40 | $1.10 |
| CUADRILLA N° 344 | 1 of.pintor + 2 ayudante A. | JOR | 0.001333 | $856.13 | $1.14 |
| Suma de Mano de Obra | $4.17 | ||||
| Equipo | |||||
| EQUIPO DE CORTE | EQUIPO DE CORTE DE OXI-ACETILENO CON ACCESORIOS HARRIS | HR | 0.013880 | $0.59 | $0.01 |
| ESMERILADORA | Esmeriladora | HR | 0.028440 | $9.25 | $0.26 |
| SOLDADORA | Soldadora Miller Mod. S64 | HR | 0.018310 | $3.75 | $0.07 |
| GRUA | Grua de 20 ton. | HR | 0.002300 | $251.44 | $0.58 |
| EQUIPO DE PINTURA | Equipo de pintura IPSA | HR | 0.035290 | $2.26 | $0.08 |
| Suma de Equipo | $1.00 | ||||
| Auxiliar | |||||
| SAND-BLAST ESTRUCTUR | APLICACIÓN DE SAND-BLAST A METAL BLANCO A TODOS LOS ELEMENTOS DE LA ESTRUCTURA METALICA | M2 | 0.030000 | $3.25 | $0.10 |
| Suma de Auxiliar | $0.10 | ||||
| Costo Directo | $18.58 |