| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| G13 | GUARNICION DE CONCRETO PREMEZCLADO F'C= 200 KG/CM2 ARMADA CON 3 VARILLAS # 3 Y ESTRIBOS 2.5 @ 15 CM. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.050000 | $37.70 | $1.89 |
| CONC.PREMEZ.F-C=200 | Concreto Premezclado F'c=200 Kg/cm2 T.M.A. 3/4" revenimiento tiro directo | M3 | 0.105000 | $860.00 | $90.30 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.050000 | $11.00 | $11.55 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 1.000000 | $4.34 | $4.34 |
| Suma de Material | $108.08 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.055556 | $661.54 | $36.75 |
| Suma de Mano de Obra | $36.75 | ||||
| Costo Directo | $144.83 |