| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| F4 | CIMBRA COMUN EN FRONTERA DE PISO DE 10 CMS DE ALTURA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BARROTE 1 1/2" X 3 1 | Barrote 1 1/2" x 3 1/2" x 8 1/4' | pt | 0.200000 | $7.00 | $1.40 |
| POLÍN 3 1/2 X 3 1/2" | Polín 3 1/2 x 3 1/2" x 8 1/4' | pt | 0.150000 | $7.00 | $1.05 |
| ACE#2 | Acero de refuerzo núm. 2 (1/4" ) fyp = 2530 kg/ml | kg | 0.020000 | $7.00 | $0.14 |
| CIMBRAPLAY 16 MM. | cimbraplay de contacto de 16 mm. | M2 | 0.020000 | $95.00 | $1.90 |
| ALAMBRE RECOCIDO | ALAMBRE RECOCIDO | Kg | 0.020000 | $14.00 | $0.28 |
| DIESEL | DESMOLDANTE | Lt | 0.035000 | $6.10 | $0.21 |
| CLAVO CON CABEZA DE | Clavo con cabeza de 3" | kg | 0.030000 | $19.13 | $0.57 |
| ACE#3 | ACERO DE REFUERZO DE 3/8" #3 f`y = 4200 kg/ml | KG | 0.040000 | $7.00 | $0.28 |
| Suma de Material | $5.84 | ||||
| Mano de Obra | |||||
| CUAD OC 11 | CUAD. 1 OF. CARPINTERO O.N. + 1AYTE. | jor | 0.020000 | $661.54 | $13.23 |
| Suma de Mano de Obra | $13.23 | ||||
| Costo Directo | $19.07 |