| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| F3 | BANQUETA DE CONCRETO F´C= 150 KG/CM2 DE 10 CMS DE ESPESRO ARMADO CON MALLA 6-6 10 X 10 ACABDO ESCOBILLADO Y JUNTAS | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| AGUA | AGUA | M3 | 0.050000 | $37.70 | $1.89 |
| MALLA 6/6 10-10 | MALLA ELECTROSOLDADA 6/6 10-10 | M2 | 1.050000 | $11.00 | $11.55 |
| DUELA ECONOMICA 3/4" | Duela Economica 3/4" x 3 1/2" x 8 1/4' | pt | 1.000000 | $4.34 | $4.34 |
| Suma de Material | $17.78 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.100000 | $661.54 | $66.15 |
| Suma de Mano de Obra | $66.15 | ||||
| Auxiliar | |||||
| CONCRETO F-C=150 H/O | Concreto f'c=150 kg/cm2 hecho en obra agregado maximo gravilla 3/4" | M3 | 0.105000 | $780.97 | $82.00 |
| Suma de Auxiliar | $82.00 | ||||
| Costo Directo | $165.93 |