| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PLA-015 | PLANTILLA APISONADA AL 85% PROCTOR, EN ZANJAS CON MATERIAL PRODUCTO DE LA EXCAVACION. INCLUYE: COMPACTADO MANUAL EN FONDO DE CEPA | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.256000 | $5.61 | $1.44 |
| MADERA PINO BARROTE | MADERA DE PINO DE 3A. EN BARROTE DE 2" X 4" | PT | 0.256000 | $5.61 | $1.44 |
| CONCRETO PRE F´C=100 | CONCRETO PREMEZCLADO F'C = 100 KG/CM2 | m3 | 0.050000 | $608.00 | $30.40 |
| CONCRETO PRE F´C=100 | CONCRETO PREMEZCLADO F'C = 100 KG/CM2 | m3 | 0.050000 | $608.00 | $30.40 |
| Suma de Material | $63.67 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 09 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.033333 | $669.66 | $22.32 |
| CUADRILLA NO. 09 | (1 ALBAÑIL + 1 AYUDANTE DE ALBAÑIL) | JOR | 0.033333 | $669.66 | $22.32 |
| Suma de Mano de Obra | $44.64 | ||||
| Costo Directo | $108.32 |