| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IM01-15 | CONSTRUCCION DE IMBORNAL DE 1.20 x 0.60 x 1.00 M DE PROFUNDIDAD EN MURO DE 10 CM DE ESPESOR CON CONCRETO F'c=200 KG/CM2 ARMADO CON Vs # 3 @ 15 CM EN AMBOS SENTIDOS (INCLUYE CIMBRA, COLADOS, ETC.) CON REJA METALICA DE CANAL DE 3" x 1 1/2" | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO ESTR 1 | ACERO ESTRUCTURAL EN VIGAS Y CANAL | KG | 48.200000 | $20.00 | $964.00 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 4.000000 | $49.88 | $199.52 |
| OXIGENO 1 | OXIGENO | M3 | 1.000000 | $39.00 | $39.00 |
| ACETILENO 1 | ACETILENO | KG | 1.000000 | $130.00 | $130.00 |
| Suma de Material | $1,332.52 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.050000 | $290.45 | $14.52 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.500000 | $233.90 | $116.95 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.500000 | $181.41 | $90.71 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.000000 | $169.01 | $169.01 |
| Suma de Mano de Obra | $391.19 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 1.500000 | $111.52 | $167.28 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 1.500000 | $24.34 | $36.51 |
| Suma de Equipo | $203.79 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 1.120000 | $68.74 | $76.99 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 0.720000 | $78.79 | $56.73 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 20.490000 | $22.84 | $467.99 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 7.200000 | $112.45 | $809.64 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.430000 | $1,311.84 | $564.09 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 0.500000 | $40.09 | $20.05 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 1.450000 | $76.52 | $110.95 |
| Suma de Auxiliar | $2,106.44 | ||||
| Costo Directo | $4,033.94 |