| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1150-01 | ADEME DE MADERA CERRADO | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 5.000000 | $16.15 | $80.75 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.150000 | $34.00 | $5.10 |
| Suma de Material | $85.85 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.004000 | $290.45 | $1.16 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.040000 | $233.90 | $9.36 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.040000 | $181.41 | $7.26 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.100000 | $169.01 | $16.90 |
| Suma de Mano de Obra | $34.68 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $120.53 |