| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2000-29 | DADO DE CONCRETO INCLUYE CIMBRA COMUN | M3 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.012500 | $290.45 | $3.63 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.125000 | $181.41 | $22.68 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.125000 | $169.01 | $21.13 |
| Suma de Mano de Obra | $47.43 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 1.000000 | $1,311.84 | $1,311.84 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 1.500000 | $112.45 | $168.68 |
| Suma de Auxiliar | $1,480.52 | ||||
| Costo Directo | $1,527.95 |