| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3110-01 | INSTALACION DE BROCAL Y TAPA DE CONCRETO PARA POZO DE VISITA | JGO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 1.250000 | $16.15 | $20.19 |
| CEMENTO GRIS 1 | CEMENTO GRIS NORMAL | TON | 0.010000 | $2,378.40 | $23.78 |
| Suma de Material | $43.97 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.012500 | $290.45 | $3.63 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.125000 | $233.90 | $29.24 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.125000 | $181.41 | $22.68 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.250000 | $169.01 | $42.25 |
| Suma de Mano de Obra | $97.80 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $141.77 |