| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6005-05 | REGISTRO ALBANAL CON MURO DE TABIQUE CON APLANADO INTERIOR DE 1.50 x 1.50 x 2.30 M | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.060000 | $290.45 | $17.43 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.600000 | $233.90 | $140.34 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.600000 | $181.41 | $108.85 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.600000 | $169.01 | $101.41 |
| Suma de Mano de Obra | $368.02 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 5.175000 | $68.74 | $355.73 |
| CONCRETO F-C=100 1 | CONCRETO F'C=100 KG/CM2 | M3 | 0.112500 | $1,070.25 | $120.40 |
| MURO TAB 1 | MURO DE TABIQUE | M2 | 13.800000 | $291.27 | $4,019.53 |
| APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 13.800000 | $121.86 | $1,681.67 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 2.250000 | $112.45 | $253.01 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 24.000000 | $22.84 | $548.16 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.225000 | $1,311.84 | $295.16 |
| Suma de Auxiliar | $7,273.66 | ||||
| Costo Directo | $7,641.68 |