| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IM01-02 | CONSTRUCCION DE CANAL PLUVIAL DE CONCRETO F'c= 200 KG/CM2, DE 1.00 M DE ANCHO Y 12 CM DE ESPESOR ARMADA CON MALLA ELECTROSOLDADA 66-10/10 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 1.050000 | $33.86 | $35.55 |
| Suma de Material | $35.55 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.002500 | $290.45 | $0.73 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.025000 | $233.90 | $5.85 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.025000 | $181.41 | $4.54 |
| Suma de Mano de Obra | $11.11 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.120000 | $1,311.84 | $157.42 |
| Suma de Auxiliar | $157.42 | ||||
| Costo Directo | $204.08 |