| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CA01-02 | CONSTRUCCION DE AREA DE ALMACENAMIENTO DE 5.00 x 4.00 x 2.30 DE ALTO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| PUERTA MET 1 | PUERTA METALICA DE 0.90 x 2.10 M | PZA | 1.000000 | $4,000.00 | $4,000.00 |
| Suma de Material | $4,000.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.045000 | $290.45 | $13.07 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.450000 | $233.90 | $105.26 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.450000 | $181.41 | $81.63 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.450000 | $169.01 | $76.05 |
| Suma de Mano de Obra | $276.01 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.500000 | $200.73 | $100.37 |
| Suma de Equipo | $100.37 | ||||
| Auxiliar | |||||
| TRAZO Y NIVELACION 1 | TRAZO Y NIVELACION | M2 | 30.000000 | $3.99 | $119.70 |
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 4.500000 | $68.74 | $309.33 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 9.000000 | $78.79 | $709.11 |
| DALA DE DESP 1 | DALA DE DESPLANTE DE 20 x 15 CM | ML | 18.000000 | $190.24 | $3,424.32 |
| MURO BLOCK 1 | MURO DE BLOCK DE CONCRETO DE 15 CM | M2 | 41.400000 | $163.39 | $6,764.35 |
| DALA DE CERR 1 | DALA DE CERRAMIENTO DE 20 x 15 CM | ML | 18.000000 | $190.24 | $3,424.32 |
| LOSA CONC ARM 1 | LOSA DE CONCRETO ARMADO F'C=200 KG/CM2 DE 10 CM | M2 | 20.000000 | $607.11 | $12,142.20 |
| APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 82.800000 | $121.86 | $10,090.01 |
| PISO CONCR 1 | PISO DE CONCRETO F'c=150 KG/CM2 DE 10 CM | M2 | 20.000000 | $162.77 | $3,255.40 |
| RELLENO COMPAC 1 | RELLENO COMPACTADO AL 90% | M3 | 4.500000 | $54.91 | $247.10 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 5.850000 | $76.52 | $447.64 |
| LIMPIEZA GRAL 1 | LIMPIEZA GENERAL DE LA OBRA | M2 | 30.000000 | $3.90 | $117.00 |
| Suma de Auxiliar | $41,050.47 | ||||
| Costo Directo | $45,426.85 |