| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2000-30 | DADO DE CONCRETO F'c= 150 KG/CM2 DE 0.80 x 0.80 x 0.50 EN JUNTAS DE TUBERIA INCLUYE CIMBRA Y DESCIMBRA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.020000 | $290.45 | $5.81 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.200000 | $181.41 | $36.28 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.200000 | $169.01 | $33.80 |
| Suma de Mano de Obra | $75.89 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.320000 | $1,311.84 | $419.79 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 1.400000 | $112.45 | $157.43 |
| Suma de Auxiliar | $577.22 | ||||
| Costo Directo | $653.11 |