| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1001-14 | REPOSICION DE PAVIMENTO O BANQUETA DE CONCRETO F'c= 200 KG/CM2 DE 25 CM DE ESPESOR | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 1.100000 | $33.86 | $37.25 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| CONC PREM 200 1 | CONCRETO PREMEZCLADO F'c=200 KG/CM2 | M3 | 0.250000 | $1,168.90 | $292.23 |
| Suma de Material | $331.37 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.014500 | $290.45 | $4.21 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.145000 | $233.90 | $33.92 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.145000 | $181.41 | $26.30 |
| Suma de Mano de Obra | $64.43 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR CHICOTE 1 | VIBRADOR DE CHICOTE KOHLER K-181 MOTOR GASOLINA DE 4 HP | HORA | 0.350000 | $40.78 | $14.27 |
| Suma de Equipo | $14.27 | ||||
| Costo Directo | $410.08 |