| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IM01-07 | CONSTRUCCION DE IMBORNAL DE 12.00 x 0.60 x 1.80 M DE PROFUNDIDAD EN MURO DE 10 CM DE ESPESOR CON CONCRETO F'c=200 KG/CM2 ARMADO CON Vs # 3 @ 20 CM EN AMBOS SENTIDOS (INCLUYE CIMBRA, COLADOS, ETC.) CON REJA METALICA DE CANAL DE 3" x 1" | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO ESTR 1 | ACERO ESTRUCTURAL EN VIGAS Y CANAL | KG | 477.600000 | $20.00 | $9,552.00 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 12.000000 | $49.88 | $598.56 |
| OXIGENO 1 | OXIGENO | M3 | 3.000000 | $39.00 | $117.00 |
| ACETILENO 1 | ACETILENO | KG | 3.000000 | $130.00 | $390.00 |
| Suma de Material | $10,657.56 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.400000 | $290.45 | $116.18 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 4.000000 | $233.90 | $935.60 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 4.000000 | $181.41 | $725.64 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 4.000000 | $169.01 | $676.04 |
| Suma de Mano de Obra | $2,453.46 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 8.000000 | $111.52 | $892.16 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 8.000000 | $24.34 | $194.72 |
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 1.000000 | $200.73 | $200.73 |
| Suma de Equipo | $1,287.61 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 21.600000 | $68.74 | $1,484.78 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 7.200000 | $78.79 | $567.29 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 378.000000 | $22.84 | $8,633.52 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 75.600000 | $112.45 | $8,501.22 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 7.560000 | $1,311.84 | $9,917.51 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 1.440000 | $40.09 | $57.73 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 26.208000 | $76.52 | $2,005.44 |
| Suma de Auxiliar | $31,167.49 | ||||
| Costo Directo | $45,566.12 |