| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3061-01 | INCREMENTO DEL PRECIO AL POZO DE VISITA A CADA 0.25 M DE PROFUNDIDAD | INC |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TABIQUE 1 | TABIQUE ROJO RECOCIDO DE 7*14*28 CM | PZA | 78.000000 | $3.50 | $273.00 |
| CEMENTO GRIS 1 | CEMENTO GRIS NORMAL | TON | 0.008000 | $2,378.40 | $19.03 |
| ARENA M ALEMAN 1 | ARENA MIGUEL ALEMAN | M3 | 0.125000 | $315.00 | $39.38 |
| AGUA ADQUIRIDA 1 | AGUA ADQUIRIDA | M3 | 0.050000 | $31.50 | $1.58 |
| ACERO DE REF 3/8" 1 | ACERO DE REFUERZO DE 3/8" | KG | 0.825000 | $14.08 | $11.62 |
| Suma de Material | $344.59 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.020000 | $290.45 | $5.81 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.200000 | $233.90 | $46.78 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.060000 | $181.41 | $10.88 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.800000 | $169.01 | $135.21 |
| Suma de Mano de Obra | $198.68 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $543.27 |