| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IM01-12 | CONSTRUCCION DE CANAL PLUVIAL DE CONCRETO F'c= 200 KG/CM2, DE 0.70 M DE ANCHO Y 12 CM DE ESPESOR ARMADA CON MALLA ELECTROSOLDADA 66-10/10 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 0.700000 | $33.86 | $23.70 |
| CURACRETO 1 | CURACRETO | LTO | 0.250000 | $18.00 | $4.50 |
| Suma de Material | $28.20 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.003750 | $290.45 | $1.09 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.037500 | $233.90 | $8.77 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.037500 | $181.41 | $6.80 |
| Suma de Mano de Obra | $16.66 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| CIM Y DESCIM 1 | CIMBRA Y DESCIMBRA | M2 | 0.350000 | $159.93 | $55.98 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.084000 | $1,311.84 | $110.19 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.084000 | $215.24 | $18.08 |
| Suma de Auxiliar | $184.25 | ||||
| Costo Directo | $229.12 |