| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IN01-30 | CONSTRUCCION DE IMBORNAL DE 1.53 x 0.70 x 1.00 M DE PROFUNDIDAD EN MURO DE 15 CM DE ESPESOR CON CONCRETO F'c=250 KG/CM2 ARMADO CON Vs # 4 @ 10 CM EN AMBOS SENTIDOS INCLUYE CIMBRA, COLADOS Y BROCAL Y TAPA DE FoFo | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BROC-TAPA FOFO 1 | BROCAL Y TAPA DE Fo.Fo. CON MEDIANO CIEGO DE 135 KG | JGO | 1.000000 | $3,300.00 | $3,300.00 |
| Suma de Material | $3,300.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.050000 | $290.45 | $14.52 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.500000 | $233.90 | $116.95 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.500000 | $181.41 | $90.71 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.000000 | $169.01 | $169.01 |
| Suma de Mano de Obra | $391.19 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 1.500000 | $111.52 | $167.28 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 1.500000 | $24.34 | $36.51 |
| Suma de Equipo | $203.79 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 2.200000 | $68.74 | $151.23 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 1.071000 | $78.79 | $84.38 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 158.320000 | $18.15 | $2,873.51 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 9.990000 | $112.45 | $1,123.38 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 0.991000 | $1,407.27 | $1,394.60 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 0.991000 | $215.24 | $213.30 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 0.350000 | $40.09 | $14.03 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 2.860000 | $76.52 | $218.85 |
| Suma de Auxiliar | $6,073.28 | ||||
| Costo Directo | $9,968.26 |