| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PV22-01 | FABRICACION DE RAMPAS DE ACCESO DE 5.00 X 2.50 M DE CON CONCRETO F'c=200 KG/CM2 DE 15 CM DE ESPESOR, ARMADO CON VS DE 1/2" @ 15 CM EN AMBOS SENTIDOS | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONC PREM 150 1 | CONCRETO PREMEZCLADO F'c=150 KG/CM2 | M3 | 3.130000 | $1,039.28 | $3,252.95 |
| Suma de Material | $3,252.95 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.025000 | $290.45 | $7.26 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.250000 | $233.90 | $58.48 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.250000 | $181.41 | $45.35 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.500000 | $169.01 | $84.51 |
| Suma de Mano de Obra | $195.59 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 3.750000 | $68.74 | $257.78 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 12.500000 | $78.79 | $984.88 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 167.500000 | $18.15 | $3,040.13 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 3.000000 | $112.45 | $337.35 |
| Suma de Auxiliar | $4,620.13 | ||||
| Costo Directo | $8,068.67 |