| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PV14-02 | BANQUETA DE CONCRETO PREMEZCLADO F'c=200 KG/CM2 DE 10 CM DE ESPESOR Y 1.22 M DE ANCHO ACABADO ESCOBILLADO INCLUYE EXCAVACION Y/O RELLENO COMPACTADO, CIMBRA Y DESCIMBRA Y LIMPIEZA | M2 |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 0.350000 | $16.15 | $5.65 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.020000 | $34.00 | $0.68 |
| ALAMBRE REC #18 1 | ALAMBRE RECOCIDO # 18 | KG | 0.100000 | $19.00 | $1.90 |
| DIESEL 1 | DIESEL | LTO | 0.150000 | $11.28 | $1.69 |
| CONC PREM 200 1 | CONCRETO PREMEZCLADO F'c=200 KG/CM2 | M3 | 0.105000 | $1,168.90 | $122.73 |
| CURACRETO 1 | CURACRETO | LTO | 0.250000 | $18.00 | $4.50 |
| Suma de Material | $137.16 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.005000 | $290.45 | $1.45 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.050000 | $233.90 | $11.70 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.050000 | $181.41 | $9.07 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.050000 | $169.01 | $8.45 |
| Suma de Mano de Obra | $30.67 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR CHICOTE 1 | VIBRADOR DE CHICOTE KOHLER K-181 MOTOR GASOLINA DE 4 HP | HORA | 0.500000 | $40.78 | $20.39 |
| Suma de Equipo | $20.39 | ||||
| Costo Directo | $188.22 |