| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3090-18 | CAJA UNION ENTRE TUBOS DE 76 CM DE DIAMETRO HASTA 3.00 M DE PROFUNDIDAD DE CONCRETO F'C=250 KG/CM2, ARMADO CON Vs # 4 @ 15 CM LOSA INFERIOR Y SUPERIOR DE 20 CM CON CONCRETO INCLUYE EXCAVACION, CIMBRA Y MARCO CON TAPA DE POLIETILENO | POZO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BROC-TAPA PVC 1 | BROCAL Y TAPA DE POLIETILENO SANITARIO (PESADO) | JGO | 1.000000 | $1,205.60 | $1,205.60 |
| ESCAL P/POZ 1 | ESCALON PARA POZOS | PZA | 5.000000 | $100.00 | $500.00 |
| Suma de Material | $1,705.60 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.100000 | $290.45 | $29.05 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.000000 | $233.90 | $233.90 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.000000 | $181.41 | $181.41 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.000000 | $169.01 | $169.01 |
| Suma de Mano de Obra | $613.37 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.500000 | $200.73 | $100.37 |
| Suma de Equipo | $100.37 | ||||
| Auxiliar | |||||
| TRAZO Y NIVELACION 1 | TRAZO Y NIVELACION | M2 | 3.600000 | $3.99 | $14.36 |
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 10.080000 | $68.74 | $692.90 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 3.600000 | $78.79 | $283.64 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 870.200000 | $18.15 | $15,794.13 |
| CIMBRA APARENTE 1 | CIMBRA APARENTE EN MURO | M2 | 39.120000 | $196.64 | $7,692.56 |
| CIMBRA APARENTE 2 | CIMBRA APARENTE EN LOSA | M2 | 2.400000 | $254.63 | $611.11 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 5.360000 | $1,407.27 | $7,542.97 |
| RELLENO COMPAC 1 | RELLENO COMPACTADO AL 90% | M3 | 2.400000 | $54.91 | $131.78 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 10.080000 | $76.52 | $771.32 |
| LIMPIEZA GRAL 1 | LIMPIEZA GENERAL DE LA OBRA | M2 | 3.600000 | $3.90 | $14.04 |
| Suma de Auxiliar | $33,548.82 | ||||
| Costo Directo | $35,968.15 |