| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IMB04-01 | CONSTRUCCION DE IMBORNAL DE 4.00 x 1.30 x 1.50 M DE PROFUNDIDAD EN MURO DE 15 CM DE ESPESOR CON CONCRETO F'c=200 KG/CM2 ARMADO CON Vs # 3 @ 20 CM EN AMBOS SENTIDOS (INCLUYE CIMBRA, COLADOS, ETC.) CON REJA METALICA DE VIGA DE 6" x 4" | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| ACERO ESTR 1 | ACERO ESTRUCTURAL EN VIGAS Y CANAL | KG | 189.740000 | $20.00 | $3,794.80 |
| ANGULO 1/4"X2"X2" 1 | ANGULO DE 2" x 2" x 1/4" | KG | 50.350000 | $20.00 | $1,007.00 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 15.650000 | $49.88 | $780.62 |
| ACETILENO 1 | ACETILENO | KG | 3.550000 | $130.00 | $461.50 |
| OXIGENO 1 | OXIGENO | M3 | 5.220000 | $39.00 | $203.58 |
| Suma de Material | $6,247.50 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.200000 | $290.45 | $58.09 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 2.000000 | $233.90 | $467.80 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 2.000000 | $181.41 | $362.82 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 4.000000 | $169.01 | $676.04 |
| Suma de Mano de Obra | $1,564.75 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 2.000000 | $111.52 | $223.04 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 2.000000 | $24.34 | $48.68 |
| Suma de Equipo | $271.72 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 7.800000 | $68.74 | $536.17 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 5.200000 | $78.79 | $409.71 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 46.000000 | $22.84 | $1,050.64 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 31.800000 | $112.45 | $3,575.91 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 2.370000 | $1,311.84 | $3,109.06 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 4.770000 | $40.09 | $191.23 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 10.140000 | $76.52 | $775.91 |
| Suma de Auxiliar | $9,648.63 | ||||
| Costo Directo | $17,732.60 |