| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CA06-02 | SUMINISTRO E INSTALACION DE PROTECCION PARA VALVULAS DE ADMISION Y EXPULSION DE AIRE Y DESFOGUES, A BASE DE ESTRUCTURA DE TUBERIA DE ACERO DE 2" DE DIAMETRO SOLDADAS DE ACUERDO A PLANO DE INSTALACION FROMANDO RECTANGULO DE 2.00 x 1.50 M ACABADO EN PINTURA ESMALTE ANTOCORROSIVA COLOR AMARILLO TRANSITO | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| OXIGENO 1 | OXIGENO | M3 | 5.000000 | $39.00 | $195.00 |
| TUBO ACERO 2" 1 | TUBO DE ACERO CED-40 DE 2" DE DIAMETRO | M | 16.400000 | $300.00 | $4,920.00 |
| ACETILENO 1 | ACETILENO | KG | 5.000000 | $130.00 | $650.00 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 8.000000 | $49.88 | $399.04 |
| PINT ESMALTE 1 | PINTURA ESMALTE ANTICORROSIVA | LTO | 1.500000 | $90.00 | $135.00 |
| Suma de Material | $6,299.04 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.400000 | $290.45 | $116.18 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.750000 | $233.90 | $175.43 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.750000 | $181.41 | $136.06 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.500000 | $169.01 | $253.52 |
| Suma de Mano de Obra | $681.18 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| SOLDADORA 300 AMP 1 | SOLDADORA LINCOLN 300 AMP MOTOR DIESEL DE 60 HP | HORA | 4.000000 | $111.52 | $446.08 |
| EQUIPO CORTE OX 1 | EQUIPO DE CORTE OXIACETILENO | HORA | 4.000000 | $24.34 | $97.36 |
| TALADRO ELECTRICO 1 | TALADRO ELECTRICO BLACK AND DECKER DE PESADO 1/4" | HORA | 4.000000 | $0.95 | $3.80 |
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 1.000000 | $200.73 | $200.73 |
| Suma de Equipo | $747.97 | ||||
| Auxiliar | |||||
| TRAZO Y NIVELACION 1 | TRAZO Y NIVELACION | M2 | 7.500000 | $3.99 | $29.93 |
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 1.600000 | $68.74 | $109.98 |
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 | 1.600000 | $1,170.99 | $1,873.58 |
| LIMPIEZA GRAL 1 | LIMPIEZA GENERAL DE LA OBRA | M2 | 7.500000 | $3.90 | $29.25 |
| Suma de Auxiliar | $2,042.74 | ||||
| Costo Directo | $9,770.93 |