| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| CA01-06 | CONSTRUCCION DE CAJA ROMPEDORA DE PRESION DE 3.00 x 1.50 x 4.00 M. DE CONCRETO F'C=200 KG/CM2, ARMADO CON 4 Vs # 3 Y E # 2 @ 20 CM LOSA INFERIOR Y SUPERIOR DE 15 CM CON CONCRETO INCLUYE EXCAVACION, CIMBRA Y MARCO CON TAPA FoFo | CAJA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BROC-TAPA FOFO 1 | BROCAL Y TAPA DE Fo.Fo. CON MEDIANO CIEGO DE 135 KG | JGO | 2.000000 | $3,300.00 | $6,600.00 |
| ESCAL P/POZ 1 | ESCALON PARA POZOS | PZA | 9.000000 | $100.00 | $900.00 |
| Suma de Material | $7,500.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.100000 | $290.45 | $29.05 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.000000 | $233.90 | $233.90 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.000000 | $181.41 | $181.41 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.000000 | $169.01 | $169.01 |
| Suma de Mano de Obra | $613.37 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| TRAZO Y NIVELACION 1 | TRAZO Y NIVELACION | M2 | 4.500000 | $3.99 | $17.96 |
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 43.500000 | $68.74 | $2,990.19 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 5.440000 | $78.79 | $428.62 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 733.350000 | $22.84 | $16,749.71 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 80.680000 | $18.15 | $1,464.34 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 77.640000 | $112.45 | $8,730.62 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 6.720000 | $1,311.84 | $8,815.56 |
| VAC DE CONC 1 | VACIADO DE CONCRETO | M3 | 6.720000 | $215.24 | $1,446.41 |
| RELLENO COMPAC 1 | RELLENO COMPACTADO AL 90% | M3 | 23.880000 | $54.91 | $1,311.25 |
| ACARREO 1ER KMS 1 | ACARREO 1er KM CAMION | M3 | 26.500000 | $76.52 | $2,027.78 |
| ACARREO KMS SUBSEC | ACARREO KMS SUBSEC CAMION | M3-KM | 132.500000 | $7.11 | $942.08 |
| LIMPIEZA GRAL 1 | LIMPIEZA GENERAL DE LA OBRA | M2 | 4.500000 | $3.90 | $17.55 |
| Suma de Auxiliar | $44,942.07 | ||||
| Costo Directo | $53,055.44 |