| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3090-17 | POZO DE VISITA TIPO CAJA PARA TUBERIA DE 61 CM DE DIAMETRO HASTA 5.00 M DE PROFUNDIDAD DE CONCRETO F'C=250 KG/CM2, ARMADO CON 6 Vs # 4 Y E # 3 @ 15 CM LOSA INFERIOR Y SUPERIOR DE 25 CM CON CONCRETO INCLUYE EXCAVACION, CIMBRA Y MARCO CON TAPA FoFo | POZO |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| BROC-TAPA FOFO 1 | BROCAL Y TAPA DE Fo.Fo. CON MEDIANO CIEGO DE 135 KG | JGO | 1.000000 | $3,300.00 | $3,300.00 |
| ESCAL P/POZ 1 | ESCALON PARA POZOS | PZA | 12.000000 | $100.00 | $1,200.00 |
| Suma de Material | $4,500.00 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.100000 | $290.45 | $29.05 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 1.000000 | $233.90 | $233.90 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 1.000000 | $181.41 | $181.41 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 1.000000 | $169.01 | $169.01 |
| Suma de Mano de Obra | $613.37 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| CAMION PLATAF 3 T 1 | CAMION PLATAFORMA FORD DE 3 TON DE CAPACIDAD | HORA | 0.500000 | $200.73 | $100.37 |
| Suma de Equipo | $100.37 | ||||
| Auxiliar | |||||
| TRAZO Y NIVELACION 1 | TRAZO Y NIVELACION | M2 | 5.000000 | $3.99 | $19.95 |
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 12.960000 | $68.74 | $890.87 |
| PLAN CONCR 1 | PLANTILLA CONCRETO F'c=100 | M2 | 4.166400 | $78.79 | $328.27 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 67.010000 | $22.84 | $1,530.51 |
| ACERO REF #4 1 | ACERO DE REFUERZO # 4 | KG. | 227.530000 | $18.15 | $4,129.67 |
| CIMBRA APARENTE 1 | CIMBRA APARENTE EN MURO | M2 | 16.320000 | $196.64 | $3,209.16 |
| CIMBRA APARENTE 2 | CIMBRA APARENTE EN LOSA | M2 | 4.170000 | $254.63 | $1,061.81 |
| CONCRETO F-C=250 1 | CONCRETO F'c=250 KG/CM2 | M3 | 3.070000 | $1,407.27 | $4,320.32 |
| MURO TAB 1 | MURO DE TABIQUE | M2 | 18.600000 | $291.27 | $5,417.62 |
| APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 18.600000 | $121.86 | $2,266.60 |
| RELLENO COMPAC 1 | RELLENO COMPACTADO AL 90% | M3 | 2.400000 | $54.91 | $131.78 |
| ACARREO KMS 1 | ACARREO 1er KM CAMION | M3 | 16.850000 | $76.52 | $1,289.36 |
| LIMPIEZA GRAL 1 | LIMPIEZA GENERAL DE LA OBRA | M2 | 5.000000 | $3.90 | $19.50 |
| Suma de Auxiliar | $24,615.42 | ||||
| Costo Directo | $29,829.15 |