| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2300-19 | SUMINISTRO E INSTALACION DE TOMA DOMICILIARIA T-5 DE COBRE DE 3/4" (14.00 M DE LONGITUD) INCLUYE EXCAVACION A MANO Y RELLENO A VOLTEO | TOMA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO COBRE 3/4 1 | TUBO DE COBRE DE 3/4" DE DIAMETRO | M | 14.000000 | $135.05 | $1,890.70 |
| ABRAZ PVC 3*3/4 1 | ABRAZADERA DE PVC DE 3" X 3/4" | PZA | 1.000000 | $60.50 | $60.50 |
| LLAVE INSER 3/4 1 | LLAVE INSERCION DE COBRE DE 3/4" | PZA | 1.000000 | $367.43 | $367.43 |
| LLAVE CUADRO 3/4 1 | LLAVE CUADRO DE COBRE DE 3/4" | PZA | 1.000000 | $281.51 | $281.51 |
| CONC MACHO CO 3/4 1 | CONECTOR MACHO DE COBRE DE 3/4" | PZA | 2.000000 | $30.42 | $60.84 |
| CODO COBRE 3/4 1 | CODO DE COBRE A COBRE DE 3/4" | PZA | 3.000000 | $18.62 | $55.86 |
| CODO CO FO RO 3/4 1 | CODO DE COBRE FIERRO ROSCA INTERIOR DE 3/4" | PZA | 3.000000 | $90.09 | $270.27 |
| LLAVE PASO 3/4 1 | LLAVE PASO DE COBRE DE 3/4" | PZA | 1.000000 | $87.92 | $87.92 |
| MEDIDOR KENT 3/4 1 | MEDIDOR CICASA DE 3/4" DE DIAMETRO | PZA | 1.000000 | $692.50 | $692.50 |
| LLAVE JARDIN 3/4 1 | LLAVE JARDIN DE COBRE DE 3/4" | PZA | 1.000000 | $41.20 | $41.20 |
| COPLE COBRE 3/4 1 | COPLE DE COBRE DE 3/4" | PZA | 2.000000 | $13.20 | $26.40 |
| Suma de Material | $3,835.13 | ||||
| Auxiliar | |||||
| TRAZO Y NIVELACION 1 | TRAZO Y NIVELACION | M2 | 14.000000 | $3.99 | $55.86 |
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 2.800000 | $68.74 | $192.47 |
| INST TUB COB 3/4 1 | INSTALACION DE TUBERIA DE COBRE DE 3/4" | M | 14.000000 | $6.04 | $84.56 |
| INS PZA ESP CO 3/4 1 | INSTALACION DE PIEZAS ESPECIALES DE COBRE DE 3/4" | PZA | 13.000000 | $8.78 | $114.14 |
| INST CONX COB 3/4 1 | INSTALACION DE CONEXION DE COBRE DE 3/4" | PZA | 4.000000 | $7.65 | $30.60 |
| SOLD TUB CO 3/4 1 | SOLDADURA DE TUBERIA DE COBRE DE 3/4" | JTA | 9.000000 | $6.69 | $60.21 |
| INS PZA ESP PVC 3" 1 | INSTALACION DE PIEZAS ESPECIALES DE PVC DE 3" | PZA | 1.000000 | $28.62 | $28.62 |
| INS ML ADC CO 3/4 1 | INSTALACION DE TOMA METROS ADICIONALES T-5 DE COBRE DE 3/4" | M | 8.000000 | $20.38 | $163.04 |
| RELLENO A VOLTEO 1 | RELLENO A VOLTEO | M3 | 2.800000 | $20.75 | $58.10 |
| Suma de Auxiliar | $787.60 | ||||
| Costo Directo | $4,622.73 |