| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 3121-01 | INCREMENTO DEL PRECIO DE LA CAIDA POR CADA 0.50 M MAS CAIDA | INC |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CEMENTO GRIS 1 | CEMENTO GRIS NORMAL | TON | 0.006000 | $2,378.40 | $14.27 |
| ARENA M ALEMAN 1 | ARENA MIGUEL ALEMAN | M3 | 0.010000 | $315.00 | $3.15 |
| GRAVA M ALEMAN 1 | GRAVA MIGUEL ALEMAN | M3 | 0.009500 | $310.00 | $2.95 |
| AGUA ADQUIRIDA 1 | AGUA ADQUIRIDA | M3 | 0.001000 | $31.50 | $0.03 |
| Suma de Material | $20.40 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.012500 | $290.45 | $3.63 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.125000 | $233.90 | $29.24 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.125000 | $181.41 | $22.68 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.625000 | $169.01 | $105.63 |
| Suma de Mano de Obra | $161.18 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Costo Directo | $181.57 |