| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IM01-09 | CONSTRUCCION DE IMBORNAL DE 1.00 x 1.00 x 2.10 M DE PROFUNDIDAD EN MURO DE 12 CM DE ESPESOR CON CONCRETO F'c=200 KG/CM2 ARMADO CON Vs # 3 @ 20 CM EN AMBOS SENTIDOS Y MALLA ELECTROMALLA (INCLUYE CIMBRA, COLADOS, ETC.) | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MALLA ELEC 6-6/6-6 1 | MALLA ELECTROSOLDADA 6-6/6-6 | M2 | 2.220000 | $33.86 | $75.17 |
| ACERO ESTR 1 | ACERO ESTRUCTURAL EN VIGAS Y CANAL | KG | 4.000000 | $20.00 | $80.00 |
| ACETILENO 1 | ACETILENO | KG | 0.200000 | $130.00 | $26.00 |
| OXIGENO 1 | OXIGENO | M3 | 0.200000 | $39.00 | $7.80 |
| SOLDADURA E-6010 1 | SOLDADURA E-6010 | KG | 0.600000 | $49.88 | $29.93 |
| Suma de Material | $218.90 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.025000 | $290.45 | $7.26 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.250000 | $233.90 | $58.48 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.250000 | $181.41 | $45.35 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.500000 | $169.01 | $84.51 |
| Suma de Mano de Obra | $195.59 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 0.640000 | $68.74 | $43.99 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 68.300000 | $22.84 | $1,559.97 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 20.150000 | $112.45 | $2,265.87 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 1.090000 | $1,311.84 | $1,429.91 |
| Suma de Auxiliar | $5,299.74 | ||||
| Costo Directo | $5,714.23 |