| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 1005-01 | TRAZO Y NIVELACION EN EL AREA DE TRABAJO | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA P/CIMBRA 1 | MADERA PARA CIMBRA | PT | 0.090000 | $16.15 | $1.45 |
| CLAVO 1/2" 1 | CLAVO 1/2" | KG | 0.010000 | $34.00 | $0.34 |
| CALHIDRA 1 | CALHIDRA | SACO | 0.010000 | $33.00 | $0.33 |
| HILO DE PLASTICO 1 | HILO DE PLASTICO PARA TRAZO | ROLLO | 0.002000 | $40.00 | $0.08 |
| PINTURA EN BOTE 1 | PINTURA EN BOTE | PZA | 0.002500 | $76.00 | $0.19 |
| Suma de Material | $2.39 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.000200 | $290.45 | $0.06 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.003000 | $233.90 | $0.70 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.004000 | $181.41 | $0.73 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.002000 | $169.01 | $0.34 |
| Suma de Mano de Obra | $1.82 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| EQUIPO TOPOGRAFIA 1 | EQUIPO DE TOPOGRAFIA MARCA DUMPY MODELO CH-5 | HORA | 0.025000 | $36.99 | $0.92 |
| CAMIONETA PICK-UP 1 | CAMIONETA PICK-UP FORD DE 3/4 TON DE CAP (EFECTIVA) | HORA | 0.002500 | $219.49 | $0.55 |
| Suma de Equipo | $1.47 | ||||
| Costo Directo | $5.69 |