| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 6005-03 | REGISTRO ALBANAL CON MURO DE TABIQUE CON APLANADO INTERIOR DE 0.80 x 0.80 x 1.00 M | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.031300 | $290.45 | $9.09 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.312500 | $233.90 | $73.09 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.312500 | $181.41 | $56.69 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.625000 | $169.01 | $105.63 |
| Suma de Mano de Obra | $244.51 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 1.000000 | $68.74 | $68.74 |
| CONCRETO F-C=100 1 | CONCRETO F'C=100 KG/CM2 | M3 | 0.032000 | $1,070.25 | $34.25 |
| MURO TAB 1 | MURO DE TABIQUE | M2 | 3.200000 | $291.27 | $932.06 |
| APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 3.200000 | $121.86 | $389.95 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 0.960000 | $112.45 | $107.95 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 5.570000 | $22.84 | $127.22 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.064000 | $1,311.84 | $83.96 |
| Suma de Auxiliar | $1,744.13 | ||||
| Costo Directo | $1,988.64 |