| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PV16-02 | RENIVELACION DE CAJA DE VALVULAS INCLUYE EXCAVACION, RELLENO, CIMBRA, TABIQUE, CONCRETO, ETC. | CAJA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.035000 | $290.45 | $10.17 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.350000 | $233.90 | $81.87 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.350000 | $181.41 | $63.49 |
| Suma de Mano de Obra | $155.52 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 1.690000 | $68.74 | $116.17 |
| MURO TAB 1 | MURO DE TABIQUE | M2 | 4.800000 | $291.27 | $1,398.10 |
| APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 4.800000 | $121.86 | $584.93 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 0.500000 | $112.45 | $56.23 |
| CONCRETO F-C=150 1 | CONCRETO F'c=150 KG/CM2 | M3 | 0.100000 | $1,170.99 | $117.10 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 0.563300 | $40.09 | $22.58 |
| Suma de Auxiliar | $2,295.10 | ||||
| Costo Directo | $2,450.63 |