| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2401-01 | REPOSICION DE CONEXION DE DESCARGA (CONCRETO) INCLUYE MATERIALES Y MANO DE OBRA | REP-DESC |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| TUBO C-S 15 CM 1 | TUBO CONCRETO SIMPLE DE 15 CM | M | 1.000000 | $145.00 | $145.00 |
| CODO-SL CONC 15 CM 1 | CODO-SLANT DE CONCRETO SIMPLE DE 15 CM | JGO | 1.000000 | $750.00 | $750.00 |
| Suma de Material | $895.00 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 0.840000 | $68.74 | $57.74 |
| PLANT APIS 1 | PLANTILLA APISONADO | M3 | 0.060000 | $52.49 | $3.15 |
| INST TUB CON 15 CM 1 | INSTALACION DE TUBERIA CONCRETO DE 15 CM | M | 1.000000 | $30.18 | $30.18 |
| CONEX DOM (CONC) 1 | CONEXION DOMICILIARIA (CONCRETO) | JGO | 1.000000 | $59.18 | $59.18 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 0.713000 | $40.09 | $28.58 |
| ACA TUB CONC 15 CM 1 | ACARREO DE TUBERIA CONCRETO DE 15 CM | M | 1.000000 | $16.08 | $16.08 |
| Suma de Auxiliar | $194.92 | ||||
| Costo Directo | $1,089.92 |