| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2403-02 | REPOSICION DE CONEXION DE DESCARGA (PVC) INCLUYE MANO DE OBRA | REP-DESC |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 0.840000 | $68.74 | $57.74 |
| PLANT APIS 1 | PLANTILLA APISONADO | M3 | 0.060000 | $52.49 | $3.15 |
| INST TUB PVC 6" 1 | INSTALACION DE TUBERIA SANITARIA DE PVC DE 6" | M | 1.000000 | $11.99 | $11.99 |
| CONEX DOM (PVC) 1 | CONEXION DOMICILIARIA (PVC) | JGO | 1.000000 | $52.61 | $52.61 |
| RELLENO APISONADO 1 | RELLENO APISONADO | M3 | 0.713000 | $40.09 | $28.58 |
| ACA TUB PVC 6" 1 | ACARREO DE TUBERIA DE PVC DE 6" DE DIAMETRO | M | 1.000000 | $6.03 | $6.03 |
| Suma de Auxiliar | $160.11 | ||||
| Costo Directo | $160.11 |