| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 2241-13 | CAJA PARA OPERACION DE VALVULA TIPO 13 DE 2.30 X 1.60 M SIN TAPA | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.033300 | $290.45 | $9.67 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.333300 | $233.90 | $77.96 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.333300 | $181.41 | $60.46 |
| Suma de Mano de Obra | $148.09 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| EXCAV MANO SECO 1 | EXCAVACION MANO SECO | M3 | 10.320000 | $68.74 | $709.40 |
| PEDAC TABIQ 1 | PEDACERIA DE TABIQUE | M2 | 6.180000 | $30.99 | $191.52 |
| CONCRETO F-C=100 1 | CONCRETO F'C=100 KG/CM2 | M3 | 0.620000 | $1,070.25 | $663.56 |
| MURO TAB 1 | MURO DE TABIQUE | M2 | 10.700000 | $291.27 | $3,116.59 |
| DALA CONCRETO 1 | DALA DE CONCRETO 2 Vs #3 | M | 0.249000 | $157.83 | $39.30 |
| APLANADO C/1:4 1 | APLANADO CON MORTERO 1:4 | M2 | 10.140000 | $121.86 | $1,235.66 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 1.170000 | $112.45 | $131.57 |
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 114.000000 | $22.84 | $2,603.76 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.921000 | $1,311.84 | $1,208.20 |
| Suma de Auxiliar | $9,899.55 | ||||
| Costo Directo | $10,047.65 |