| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| PV13-01 | GUARNICION TIPO PECHO PALOMA (SECC = 0.10625 M3/ML) CON CONCRETO PREMEZCLADO F'c=150 KG/CM2 CON MATERIALES DE LA REGION INCLUYE PASAJUNTAS @ 3.0 M EXCAVACION Y/O RELLENO COMPACTADO, CIMBRA Y DESCIMBRA Y LIMPIEZA | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CIMB MET GUAR 1 | CIMBRA METALICA PARA GUARNICION | ML | 1.000000 | $23.00 | $23.00 |
| CELOTEX 13MM 1 | CELOTEX JUNTA 1/8" | M2 | 0.160000 | $105.00 | $16.80 |
| CONC PREM 150 1 | CONCRETO PREMEZCLADO F'c=150 KG/CM2 | M3 | 0.109500 | $1,039.28 | $113.80 |
| CURACRETO 1 | CURACRETO | LTO | 0.100000 | $18.00 | $1.80 |
| Suma de Material | $155.40 | ||||
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.004000 | $290.45 | $1.16 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.040000 | $233.90 | $9.36 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.040000 | $181.41 | $7.26 |
| OBRERO GENERAL 1 | OBRERO GENERAL | JOR | 0.040000 | $169.01 | $6.76 |
| Suma de Mano de Obra | $24.53 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| VIBRADOR CHICOTE 1 | VIBRADOR DE CHICOTE KOHLER K-181 MOTOR GASOLINA DE 4 HP | HORA | 0.150000 | $40.78 | $6.12 |
| Suma de Equipo | $6.12 | ||||
| Costo Directo | $186.05 |