| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| IM01-19 | CONSTRUCCION DE CANAL PLUVIAL DE CONCRETO F'c= 200 KG/CM2, DE 4.00 M DE ANCHO Y 12 CM DE ESPESOR ARMADA CON MALLA ELECTROSOLDADA 66-10/10 | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CABO DE OFICIOS 1 | CABO DE OFICIOS | JOR | 0.008000 | $290.45 | $2.32 |
| OPERARIO PRIMERA 1 | OPERARIO PRIMERA | JOR | 0.080000 | $233.90 | $18.71 |
| AYUDANTE OPERARIO 1 | AYUDANTE OPERARIO | JOR | 0.080000 | $181.41 | $14.51 |
| Suma de Mano de Obra | $35.55 | ||||
| Herramienta | |||||
| HERRAMIENTA MENOR 1 | HERRAMIENTA MENOR | (%)mo | 0.030000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| ACERO REF #3 1 | ACERO DE REFUERZO # 3 | KG | 2.000000 | $22.84 | $45.68 |
| CIMBRA COMUN 1 | CIMBRA COMUN | M2 | 0.400000 | $112.45 | $44.98 |
| CONCRETO F-C=200 1 | CONCRETO F'c=200 KG/CM2 | M3 | 0.008000 | $1,311.84 | $10.49 |
| DALA CONCRETO 1 | DALA DE CONCRETO 2 Vs #3 | M | 1.000000 | $157.83 | $157.83 |
| Suma de Auxiliar | $258.98 | ||||
| Costo Directo | $294.53 |