| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 183 | SUMINISTRO, MANEJO E INSTALACIÓN DE PLACA DE 1/4” DE ESPESOR, DE 100 X 50 mm, MATERIAL ASTM A-36. DOCUMENTOS Y PLANOS DE REFERENCIA: PTGA-P-316. ALCANCES DE ACUERDO AL ANEXO BP | PZA |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MAT183 | PLACA DE 1/4" DE ESPESOR, DE 100 X 50 mm, MATERIAL ASTM A-36. MARCA VILLACERO. | PZA | 1.000000 | $7.00 | $7.00 |
| SOLDADURA | SOLDADURA ELECTRODO REVESTIDO TIPO E-6010, MARCA INFRA | KGS | 0.010000 | $45.00 | $0.45 |
| SOL032 | DISCO ABRASIVO DE 1/8" DE ESPESOR POR 7 7/8" DE DIAMETRO MARCA AUSTROMEX. | PIEZA | 0.010000 | $54.85 | $0.55 |
| C004SGP | TRAPO LIMPIO DE ALGODON | KG | 0.010000 | $26.50 | $0.27 |
| SOL001 | GAS ACETILENO, MARCA INFRA | KG | 0.010000 | $168.32 | $1.68 |
| SOL002 | GAS OXIGENO, MARCA INFRA | M3 | 0.020000 | $64.98 | $1.30 |
| CEPI | CEPILLO DE ALAMBRE | PZA | 0.001000 | $25.00 | $0.03 |
| Suma de Material | $11.27 | ||||
| Mano de Obra | |||||
| CUA28 | CUADRILLA TUBERO + AYUDANTE | JOR | 0.014286 | $1,060.24 | $15.15 |
| CUA01 | CUADRILLA DE SOLDADOR + AYUDANTE | JOR | 0.014286 | $1,159.92 | $16.57 |
| Suma de Mano de Obra | $31.72 | ||||
| Herramienta | |||||
| %MO01 | HERRAMIENTA MENOR | (%)MO | 0.025000 | $0.00 | $0.00 |
| %MO02 | EQUIPO DE SEGURIDAD | (%)MO | 0.025000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Equipo | |||||
| AME-56 | CAMION PLATAFORMA CAPACIDAD DE 10 TONELADAS, CON GRUA PLUMA TIPO HIAB-650, DE 5 TONELADAS DE CAPACIDAD, MARCA INTERNATIONAL, MODELO 2009 | HORA | 0.002500 | $423.22 | $1.06 |
| AME-01 | ANDAMIOS MULTIFUNCIONALES DE ALUMINIO TIPO ATLAS | HORA | 0.003333 | $8.97 | $0.03 |
| ESME-1 | ESMERILADORA ANGULAR | HORA | 0.012500 | $2.80 | $0.04 |
| AME-15 | ESCALERAS DE ALUMINIO TIPO RECTA, MARCA CUPRUM. | HORA | 0.006667 | $0.87 | $0.01 |
| AME-03 | MAQUINA DE SOLDAR DE COMBUSTIÓN INTERNA DE 400 AMPS., CON SUS ACCESORIOS (CABLES PORTAELECTRODO, CABLE DE TIERRA CALIBRE 2/0 AWG), MARCA MILLER. | HORA | 0.006667 | $82.76 | $0.55 |
| Suma de Equipo | $1.68 | ||||
| Auxiliar | |||||
| RA-28 | APLICACION DE PINTURA ACABADO RA-28 | M2 | 0.010000 | $106.38 | $1.06 |
| RP-6 | APLICACIÓN DE PRIMARIO, RP-6 EPOXICO POLIAMIDAS DE DOS COMPONENTES | M2 | 0.010000 | $99.42 | $0.99 |
| AUX-93 | LIMPIEZA CON CHORRO DE ARENA A METAL BLANCO (SANDBLAST) | M2 | 0.010000 | $152.26 | $1.52 |
| Suma de Auxiliar | $3.58 | ||||
| Costo Directo | $48.25 |