| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| GUA021V01 | GUARNICION RECTA O CURVA, DE CONCRETO PREMEZCLADO f´c= 200 KG/CM2, RECTA O CURVA, CIMBRA APARENTE, SECCION 15 X 20 X 40 CM., PINTURA DE TRAFICO EN CARAS VISIBLES EN COLOR AMARILLO (SE APLICARA UN PRIMARIO VINILICO Y DESPUES EL ACABADO, EN COLOR AMARILLO . | M |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| CONCRETO PRE-04 | CONCRETO PREMEZCLADO DE F'C= 200 KG/CM2 CON CEMENTO CPO 30 RS | M3 | 0.077000 | $740.00 | $56.98 |
| SELLADOR VINILICO | SELLADOR VINILICO 5X1 | LT | 0.100000 | $26.18 | $2.62 |
| PINTURA-06 | THINNER | LT. | 0.100000 | $13.39 | $1.34 |
| PINTURA-01 | PINTURA AMARILLO TRAFICO | LT | 0.150000 | $41.78 | $6.27 |
| CIMBRA-04 | MADERA DE PINO | PT | 0.900000 | $8.00 | $7.20 |
| CIMBRA-01 | CIMBRAPLAY | M2 | 0.100000 | $89.22 | $8.92 |
| CIMBRA-02 | CLAVO | Kg. | 0.040000 | $19.13 | $0.77 |
| Suma de Material | $84.09 | ||||
| Mano de Obra | |||||
| CUADRILLA NO. 11 | (1 Of. Carpintero O.N. + 1Ayte). | Jor | 0.083333 | $442.37 | $36.86 |
| CUADRILLA NO. 18 | (1 Of. Pintor +2 Ayudante). | Jor | 0.023256 | $592.40 | $13.78 |
| CUADRILLA NO. 09 | (1 Of. Albanil + 1 Peón) | Jor | 0.035714 | $452.77 | $16.17 |
| Suma de Mano de Obra | $66.81 | ||||
| Costo Directo | $150.90 |