| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| 47 | DALA O CADENA CERRAMIENTO, INCLUYE CIMBRA Y DESCIMBRA SECCION=15 X 20 CM, CONCRETO F'C=150 KG/CM2-3/4", REFORZADA CON 4 VARILLAS R.N. DE 3/8" ESTRIBOS DE 1/4" A/C 30 CM | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Mano de Obra | |||||
| CUADRILLA ALBAÑIL-1 | (1 Of. Albanil + 1 Peón) | JOR | 0.142857 | $529.86 | $75.69 |
| Suma de Mano de Obra | $75.69 | ||||
| Equipo | |||||
| MAQUINARIA-23 | VIBRADOR CONCRETO | HR** | 0.500000 | $10.73 | $5.37 |
| Suma de Equipo | $5.37 | ||||
| Auxiliar | |||||
| ACERO | ACERO PARA CIMENTACION | TON | 0.003290 | $12,337.83 | $40.59 |
| ANDAMIO 2 MTS | ANDAMIO DE 2.00 MTS DE ALTURA | DIA | 0.125000 | $27.26 | $3.41 |
| CONCRETO 150 KG/CM2 | CONCRETO DE F'C= 150KG/CM2 HECHO EN OBRA AGREGADO MAXIMO 3/4. | M3 | 0.030000 | $840.13 | $25.20 |
| CIMBRA EN ESTRUC D C | CIMBRA PARA COLUMNAS | M2 | 0.400000 | $167.43 | $66.97 |
| Suma de Auxiliar | $136.17 | ||||
| Costo Directo | $217.23 |