| Clave | Descripción del Análisis de Precio Unitario | Unidad |
| A7-03 | PERFILADO VOLEADO DE ARISTAS VIVAS CON MORTERO CEMENTO ARENA 1:5, INCLUYE: MATERIALES Y MANO DE OBRA. | ML |
| Clave | Descripción | Unidad | Cantidad | Costo | Importe |
| Material | |||||
| MADERA-3 | MADERA DE PINO DE 3A. EN POLIN DE 4" X 4" | PT | 0.300000 | $6.50 | $1.95 |
| AGUA | AGUA | M3 | 0.020000 | $35.00 | $0.70 |
| Suma de Material | $2.65 | ||||
| Mano de Obra | |||||
| CUAD OC 09 | CUAD. 1 OF. ALBAÑIL + 1 PEON | jor | 0.035714 | $593.75 | $21.21 |
| Suma de Mano de Obra | $21.21 | ||||
| Herramienta | |||||
| ANDAMIOS | ANDAMIOS | (%)mo | 0.050000 | $0.00 | $0.00 |
| Suma de Herramienta | $0.00 | ||||
| Auxiliar | |||||
| MORTERO CEM-ARE 1:4 | Mortero cemento arena 1 : 4 | M3 | 0.003000 | $838.72 | $2.52 |
| Suma de Auxiliar | $2.52 | ||||
| Costo Directo | $26.37 |