| MAC-123 | Mortero cemento-arena proporcion 1:3 | m3 | 0.027500 | $1,168.52 | $32.13 |
| MAC-124 | Panel w polipropileno 1.22x2.44, 3m | pza | 0.369500 | $598.30 | $221.07 |
| MAC-125 | Madera pino 3a, 4" x 4m x 8.25’ | pt | 0.286000 | $9.33 | $2.67 |
| MAC-019 | Madera pino 3a, 2" x 4" x 8.25' | pt | 0.040300 | $9.33 | $0.38 |
| MAC-020 | Clavo de 2 1/2" (6.35cm) de largo | kg | 0.034500 | $21.90 | $0.76 |
| MAC-126 | Tira de union de 2.44 m de largo | trm | 0.470300 | $9.66 | $4.54 |
| MAC-054 | Alambre recocido calibre 18 | kg | 0.023400 | $14.78 | $0.35 |
| MAC-058 | Acero de refuerzo numero 3, 3/8" | ton | 0.002500 | $9,975.76 | $24.94 |
| MAC-003 | Agua (toma municipal) | m3 | 0.017500 | $5.20 | $0.09 |
| MAC-123 | Mortero cemento-arena proporcion 1:3 | m3 | 0.027500 | $1,168.52 | $32.13 |
| MAC-124 | Panel w polipropileno 1.22x2.44, 3m | pza | 0.369500 | $598.30 | $221.07 |
| MAC-125 | Madera pino 3a, 4" x 4m x 8.25’ | pt | 0.286000 | $9.33 | $2.67 |
| MAC-019 | Madera pino 3a, 2" x 4" x 8.25' | pt | 0.040300 | $9.33 | $0.38 |
| MAC-020 | Clavo de 2 1/2" (6.35cm) de largo | kg | 0.034500 | $21.90 | $0.76 |
| MAC-126 | Tira de union de 2.44 m de largo | trm | 0.470300 | $9.66 | $4.54 |
| MAC-054 | Alambre recocido calibre 18 | kg | 0.023400 | $14.78 | $0.35 |
| MAC-058 | Acero de refuerzo numero 3, 3/8" | ton | 0.002500 | $9,975.76 | $24.94 |
| MAC-003 | Agua (toma municipal) | m3 | 0.017500 | $5.20 | $0.09 |
| Suma de Material | | | | $573.86 |
| MOC-050 | Cuadrilla 88 (oficial especializado y dos ayudante a), incluye maestro | jor | 0.250000 | $0.00 | $0.00 |
| MOC-050 | Cuadrilla 88 (oficial especializado y dos ayudante a), incluye maestro | jor | 0.250000 | $0.00 | $0.00 |
| Suma de Mano de Obra | | | | $0.00 |
| HEC-002 | Andamios, pasarelas y escaleras | %mo | 2.000000 | $0.00 | $0.00 |
| HEC-001 | Herramienta menor | %mo | 3.000000 | $0.00 | $0.00 |
| HEC-002 | Andamios, pasarelas y escaleras | %mo | 2.000000 | $0.00 | $0.00 |
| HEC-001 | Herramienta menor | %mo | 3.000000 | $0.00 | $0.00 |
| Suma de Herramienta | | | | $0.00 |
| Concepto | | | | |
| ESTCN75-200 | Concreto fc= 200 kg/cm2 en estructura, tma 3/4" hecho en obra, vaciado manualmente, vibrado y curado, incluye materiales, desperdicios, mano de obra y equipo | m3 | 0.055000 | $5,812.80 | $319.70 |
| ESTCN75-200 | Concreto fc= 200 kg/cm2 en estructura, tma 3/4" hecho en obra, vaciado manualmente, vibrado y curado, incluye materiales, desperdicios, mano de obra y equipo | m3 | 0.055000 | $5,812.80 | $319.70 |
| Suma de Concepto | | | | $639.40 |
| Costo Directo | | | | $1,213.26 |